			The client is a Fastener company., an American wholly owned enterprise located in Suzhou Industrial Park, which manufactures aviation fasteners and industrial fasteners and is a leading global supplier of aviation fasteners
   ?The customer pain points
     Outsourcing costs are too high  
  
   ?Wastewater production process & composition  
     1.Name: : Cleaning waste liquid
     2.Process: Grinding/pickling/rinsing with centerless grinder
     3.Ingredients: Cleaning agent/metal particles/grease
  
     ?Customer original processing method & cost  
    1.
    2.0.6T waste water is produced daily, costing 4000 RMB /Ton;;
     3.The total cost of daily disposal is 2400 RMB
    1.
2.Customer's choice: pre-filtration system +LT-0.6T cryoevaporator.
				On-site Operation
			1. After operation of our LT-0.6T low-temperature evaporator, 95% of the distilled water in the stock solution can be reused up to standard, and the remaining 5% of the concentrated solution can be outsourced, saving the annual cost of about 700,000 yuan;